MRP Monthly lot size

[日期:2006-10-15] 来源:sap-img  作者:sapsky [字体: ]
MRP Monthly lot size

Appreciated if some guide can be provided.  
MRP lot size has been set to MB (Monthly lot size) 

It is known that with this setting, material are always bring in on the first working day of the month. 
Ex: Dep requirement 26-10-04 100 pcs 
Dep requirement 30-10-04 190 pcs 

When MRP completion, the PR item shown 1-10-2004 290 pcs, is that any possible to bring in material just right before dependant requirement 26-10-04 say about 24 or 25 of the month. 
Because. we dont tend to keep more stocks until actual requirement. 

Any comment are welcome. 

In that case you might like to consider lot size key WB (weekly). It will bring in material at the first working day of the week. In your case it is Oct 25, 2004

But in this case, I will have increase administrative cost on monitoring the material lot weekly. 
I want to have monthly lot size that group all the requirement, but bring in material as close as possible on the first requirement. 
Any comment are welcome.. 

How about manually change delivery date in PO item

Check your config. in OMI4 - scheduling may by ''1'" for Lot size of MB. 
Change to Blank. 

Friend PPS is correct, Schedule the "REQUIREMENTS DATE = DELIVERY DATE" option in Customizing for Lot Size MB (use Blank instead of 1) & your reqt 'll be met... 

We have similar problem and when I applied your solution, the proposed requirement date is perfect. 



阅读:
录入:sapsky

评论 】 【 推荐 】 【 打印
上一篇:[推荐]Planning Strategy Selection
下一篇:Reservation Not Created During MRP Run
相关文章      
本文评论       全部评论
发表评论


点评: 字数
姓名:

  • 尊重网上道德,遵守中华人民共和国的各项有关法律法规
  • 承担一切因您的行为而直接或间接导致的民事或刑事法律责任
  • 本站管理人员有权保留或删除其管辖留言中的任意内容
  • 本站有权在网站内转载或引用您的评论
  • 参与本评论即表明您已经阅读并接受上述条款